Project Expenses and Hourly cost rate with QB Payroll

I have a construction company and we closely monitor employee hours by job to properly estimate project profitability.  We use TSheets for job coding, integrated with QBO Advanced and use QB Payroll.  Once time is approved in TSheets, and QB payroll runs for the payroll cycle, costs are posted to the projects coded to in TSheets.  However, the cost that shows in a project's profitability overview is only wage rage and payroll tax.  I have spent a good amount of time estimating an overhead rate and have included this rate in the Hourly Cost Rate feature within projects.  I would expect the allocated overhead cost to be included in a job's profitability, to accompany wage and payroll tax cost.  Why is this not present? At a minimum this could be?  What is the point of inputting the Hourly Cost Rate if the only way to use this rate in assessing overall project profitability is to back out payroll costs linked by QB and manually calculating the Hours X Hourly cost rate?

 

11 replies

Level 9
Jan 29, 2020 8:14 AM UTC

Hi @GregMonty,

 

The Project Profitability report contains only the itemized view of your project accounts and transactions. Since overhead is made up of many different costs, QuickBooks uses the Time Cost Report to view the hourly time costs separated from other project costs.

 

Currently, QuickBooks tracks your project labor costs in a two-part process.

 

  • First, calculate the hourly cost rate for each employee.
  • Then, add project timesheets using your hourly cost rates.

Rest assured, I'll be sending a product request to our engineers so they can consider this option to be added in the future update.

 

Please refer to this handy article for details about tracking income, costs, and profitability by project. I'm also adding our blog for your reference. Here's the link: How To Calculate And Track Overhead Costs.

 

Know that I'm always here if you need help with anything else. Thank you for posting in the Community and more power to your business.

GregMontyAuthor
Jan 30, 2020 6:37 AM UTC

@ShiellaGraceA, thank you very much for confirming my suspicions.  Interestingly enough, this feature works flawlessly if you don't have QB payroll.  I mean to say that if you just integrate TSheets with QBO without payroll, the total project labor cost calculated with Hours X Hourly cost rate (inputted from the project module) is naturally part of the Project profitability report. Exactly the way one would expect it to work.

It is the add on of QB payroll that actually causes the issue because of the need to link the payroll transaction to the cost entry in the project module. 

Like I said, completely irritating to go through all the trouble of adding the overhead burden rate to every employee, only for the rate to be disregarded when calculating profitability.  It is only when you manually calculate that you can get project profitability with Overhead burden rate.

Effectively incentivizing those that are serious about job cost to use a Payroll product other than QB/Intuit Payroll.  Seems very counter intuitive.

Aug 13, 2020 9:36 PM UTC

@ShiellaGraceA @AideQuickBooks 

 

Is there any change in this? It is mind boggling that all this data is right there yet it can't be accessed in a report that is helpful.